Home

  •   
         

  •  OPCOM: PCCB-LE-Flex Contracte reziliate eng
    Centralized Market for Electricity Bilateral Contracts – Flexible Extended Auctions Mechanism (CMBC-EA-flex)

    Cancelled contracts
    No. Seller Buyer Auction Session Code Contract no./ Signed contract date Delivery period Delivery profile Cancelled period (start date - end date) Cancel date Cancel reason Participant that cancelled the contract Publishing date
    14 S.C. LUMINA SOLAR S.A. S.C. TINMAR ENERGY S.A. VV2_111121_01_C 167/12.11.2021 20.11.2021-31.12.2027 varf 2 01.07.2023-31.12.2027 30.06.2023 Mutual agreement according to art. 21 (1) letter b) S.C. LUMINA SOLAR S.A.
    S.C. TINMAR ENERGY S.A.
    03.07.2023
    13 S.C.PHOTOVOLTAIC GREEN PROJECT S.R.L. S.C. ELECTRICAFURNIZARE S.A. CBLD_210222_04 139/22.02.2022 01.01.2023-31.12.2023 banda LD 05.01.2023-31.12.2023 05.01.2023 S.C. PHOTOVOLTAIC GREEN PROJECT S.R.L. failed to comply with the contractual obligation as in art. 10, letter (b) and  letter (d) S.C. ELECTRICAFURNIZARE S.A. 09.01.2023
    12 S.C.PHOTOVOLTAIC GREEN PROJECT S.R.L. S.C. ELECTRICAFURNIZARE S.A. CBLD_210222_02 138/22.02.2022 01.01.2023-31.12.2023 banda LD 05.01.2023-31.12.2023 05.01.2023 S.C. PHOTOVOLTAIC GREEN PROJECT S.R.L. failed to comply with the contractual obligation as in art. 10, letter (b) and  letter (d) S.C. ELECTRICAFURNIZARE S.A. 09.01.2023
    11 S.C. ADERRO G.P. ENERGY S.R.L. S.C. MONSSON TRADING S.R.L. VBLD_250321_08 EEV13/25.03.2021 01.04.2021-31.03.2022 banda LD 10.01.2022-31.03.2022 10.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letter f) in conjunction with art. 18, paragraph 2, 3 and 4 from the contract S.C. MONSSON TRADING S.R.L. 12.01.2022
    10 S.C. ELECTRIC PLANNERS S.R.L. S.C. NOVA POWER & GAS S.R.L. VBLD_230821_02 020821/23.08.2021 01.01.2022-30.06.2022 banda LD 04.01.2022-30.06.2022 04.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letter f) S.C. NOVA POWER & GAS S.R.L. 06.01.2022
    9 S.C. ELECTRIC PLANNERS S.R.L. S.C. NOVA POWER & GAS S.R.L. VBLD_230821_01 010821/23.08.2021 01.01.2022-30.06.2022 banda LD 04.01.2022-30.06.2022 04.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letter f) S.C. NOVA POWER & GAS S.R.L. 06.01.2022
    8 S.C. ADERRO G.P. ENERGY S.R.L. ENERGIATAVERDE.RO FURNIZARE S.R.L. (fost S.C. APURON ENERGY S.R.L.) CBLD_230321_08 382/23.03.2021 01.04.2021-31.03.2022 banda LD 07.01.2022-31.03.2022 07.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letters b) and f) ENERGIATAVERDE.RO FURNIZARE S.R.L. (fost S.C. APURON ENERGY S.R.L.) 05.01.2022
    7 S.C. ADERRO G.P. ENERGY S.R.L. ENERGIATAVERDE.RO FURNIZARE S.R.L. (fost S.C. APURON ENERGY S.R.L.) VBLD_150321_08 11/16.03.2021 01.04.2021-31.03.2022 banda LD 07.01.2022-31.03.2022 07.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letters b) and f) ENERGIATAVERDE.RO FURNIZARE S.R.L. (fost S.C. APURON ENERGY S.R.L.) 05.01.2022
    6 S.C. ADERRO G.P. ENERGY S.R.L. S.C. EFT FURNIZARE S.R.L. VBLD_250321_08 EEV12/25.03.2021 01.04.2021-31.03.2022 banda LD 01.01.2022-31.03.2022 01.01.2022 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letter f) S.C. EFT FURNIZARE S.R.L. 30.12.2021
    5 S.C. NEXT ENERGY PARTNERS S.R.L. COMPANIA NATIONALA DE TRANSPORT AL ENERGIEI ELECTRICE `TRANSELECTRICA` S.A. CBLD_210820_01_P C196/26.08.2020
    NE20V013/21.08.2020
    01.01.2021-31.12.2021 banda LD 11.10.2021-31.12.2021 11.10.2021 Failure to comply with the obligations of energy delivery according to Art.18, paragraph 1, letter b) and f) COMPANIA NATIONALA DE TRANSPORT AL ENERGIEI ELECTRICE `TRANSELECTRICA` S.A. 12.10.2021
    4 S.C. ALIVE CAPITAL S.A. S.C. ELECTRICA FURNIZARE S.A. VV2_250620_06 79/25.06.2020 01.07.2021-30.09.2021 varf 2 15.07.2021-30.09.2021 15.07.2021 S.C. ALIVE CAPITAL S.A. failed to comply with the contractual obligation as in art. 10, letter (b) and art. 18, paragraph (1), letter (f) S.C. ELECTRICA FURNIZARE S.A. 16.07.2021
    3 S.C. ALIVE CAPITAL S.A. S.C. ELECTRICA FURNIZARE S.A. VV2_250620_01 78/25.06.2020 01.03.2021-31.10.2021 varf 2 15.07.2021-31.10.2021 15.07.2021 S.C. ALIVE CAPITAL S.A. failed to comply with the contractual obligation as in art. 10, letter (b) and art. 18, paragraph (1), letter (f) S.C. ELECTRICA FURNIZARE S.A. 16.07.2021
    2 S.C. ALIVE CAPITAL S.A. S.C. ELECTRICA FURNIZARE S.A. VV2_120520_04 39/12.05.2020 01.01.2021-31.12.2021 varf 2 15.07.2021-31.12.2021 15.07.2021 S.C. ALIVE CAPITAL S.A. failed to comply with the contractual obligation as in art. 10, letter (b) and art. 18, paragraph (1), letter (f) S.C. ELECTRICA FURNIZARE S.A. 16.07.2021
    1 S.C. MONSSON TRADING S.R.L. S.C. CEZ VANZARE S.A. VBLD_071220_03 E511A/07.12.2020 01.03.2021-31.12.2021 banda LD 01.07.2021-31.12.2021 01.07.2021 Mutual agreement S.C. MONSSON TRADING S.R.L.
    S.C. CEZ VANZARE S.A.
    01.07.2021